A Step-by-Step Guide to Resolving Strata Building Defects & Disputes

Key Takeaways

  • OCs must enforce by-laws under the Strata Schemes Management Act 2015 (NSW): Owners Corporations (OCs) have a legal duty to act against unauthorised works to protect common property and avoid legal risks.
  • Follow a strict enforcement process: OCs must issue a formal Notice to Comply and attempt mediation via NSW Fair Trading before applying to NCAT for orders.
  • Two resolution options exist: OCs can demand removal and restoration of common property or grant retrospective approval via a special resolution by-law.
  • Act promptly to avoid complications: Delays weaken an OC’s case, especially for urgent interim orders to halt ongoing works. Once completed, removal becomes harder and costlier.
8 min read
Jump to...

Introduction

Discovering a building defect in a strata property is a common and often stressful experience for lot owners, the owners corporation, and even the developer. Resolving these issues in NSW is a complex undertaking, governed by a legislative framework that sets out crucial rights and obligations, including the statutory warranties under the Home Building Act 1989 (NSW).

This guide provides a comprehensive roadmap for navigating a building dispute. It offers a structured, step-by-step process for all parties involved, explaining how to manage defect claims, engage technical experts, and choose the most appropriate dispute resolution pathway, from mediation to formal proceedings in the NSW Civil and Administrative Tribunal (NCAT) or the courts.

Identifying, Documenting & Notifying Defects

Identifying & Documenting Each Defect

When a lot owner or strata manager first reports a potential building defect, the owners corporation must act promptly. The initial and most critical step is to create a detailed evidentiary record to form the foundation of any future claim. This begins with establishing a formal Defects Register, which methodically logs every reported issue.

This register, often a simple spreadsheet, transforms informal complaints into structured evidence. For each defect, the register must include:

Register ComponentDescription
Date of DiscoveryThe exact date the defect was first noticed or reported.
LocationThe specific area, including the lot number and room, or the precise location on the common property (e.g., “Crack on the basement car park’s western wall”).
Detailed DescriptionA clear, factual description of the problem, such as “Water staining and bubbling paint on the ceiling”.
Photographic & Video EvidenceSystematically collected high-quality, dated photos and videos for every reported defect.

Video documentation is handy for dynamic issues like water leaks, as it can show the issue in action. Additionally, the owners corporation needs to take reasonable steps to prevent any identified defects from worsening, which is the duty to mitigate loss. Failing to fulfil this duty could be used by a builder to argue that the owners corporation is partially responsible for the extent of the damage.

Formally Notifying the Builder & Developer

Once you have documented the initial defects, the next crucial step is to inform the responsible parties formally. This action is essential to preserve your legal rights under the statutory warranties provided by the Home Building Act 1989 (NSW).

The owners corporation must send a clear, written notice to the builder and the developer. This formal notification should be sent via a method that provides proof of delivery, such as registered post or an email with a read receipt.

The letter should clearly:

  • Identify the owners corporation and the property address
  • Detail the alleged defects, often by attaching a preliminary list or the Defects Register
  • Reference the builders’ and developers’ obligations under the statutory warranties
  • Invite the builder and developer to attend the site to inspect the alleged defects

Under the Home Building Act 1989 (NSW), the owners corporation has an obligation not to refuse the builder access to inspect unreasonably and, if they agree, rectify the defective building work. Unfortunately, refusing to provide reasonable access can negatively impact your position in subsequent legal proceedings.

Assembling Your Professional Team

Engaging Specialist Legal Advice

Resolving a building defect dispute almost invariably requires professional expertise. The first step should be to engage a lawyer specialising in strata and construction law. This provides the owners corporation with early, strategic guidance on:

  • The viability of a claim
  • The liable parties
  • How to ensure compliance with all legal requirements

Seeking independent legal advice from a specialist is a crucial investment that can save significant time and money.

When the lawyer engages the expert to provide legal advice and for use in anticipated litigation, the consultant’s initial report can be protected by legal professional privilege. This means the report remains confidential, allowing the legal team and the owners corporation to review the findings strategically before deciding what evidence is formally served on the builder or developer.

Commissioning a Compliant Expert Report

If a builder or developer fails to rectify a building defect, the cornerstone of a successful claim is an objective, credible expert report. This is not merely a repair quote, but formal evidence prepared by a qualified building consultant, structural engineer, or another relevant technical expert.

The expert’s primary duty is to the tribunal or court, so their report must be impartial and independent. A compliant expert report is essential for any formal proceedings in NCAT or the courts and must be prepared according to the Expert Witness Code of Conduct.

The report should include several key components:

Report ComponentDescription
A detailed list of defectsProvides a clear inventory and description of each identified building defect.
A proposed scope of worksOutlines the correct methodology to rectify each defect, ensuring compliance with the National Construction Code and relevant Australian Standards.
Detailed costingsIncludes a professional estimate of the costs required for the proposed rectification work.
A Scott ScheduleA critical document, usually a table, that methodically lists each defect, the parties’ positions, the expert’s opinion, and the estimated cost for each item.

Choosing Your Dispute Resolution Pathway

Informal Resolution Through Negotiation & Mediation

Before commencing formal legal proceedings, attempting to resolve a strata building dispute amicably is highly recommended. Informal resolution pathways offer several advantages over litigation:

  • Generally faster process
  • Less adversarial approach
  • More cost-effective solution

Direct negotiations with the builder or developer, supported by your expert reports, can often lead to an agreement for rectification or a settlement.

In NSW, complaining to NSW Fair Trading is mandatory before filing a home building claim with NCAT. This free service is designed as an early intervention to help resolve disputes. The process typically involves:

  • An on-site meeting with a Fair Trading inspector, the owners corporation, and the builder or developer
  • The inspector facilitates a discussion to clarify the issues and broker an agreement

This dispute resolution process can lead to several potential outcomes:

  • A mediated agreement resolving the matter without further action
  • A legally binding Rectification Order compelling the builder to fix specified defects (if the inspector finds the work defective)
  • A letter authorising you to proceed to NCAT (if the matter is too complex or an agreement cannot be reached)

Formal Litigation in the NCAT & the Courts

If informal methods and mediation fail, the next step is to commence formal legal proceedings. The two primary forums in NSW for a building dispute are NCAT and the courts, with the correct choice depending on the claim’s value and complexity.

NCAT is the most common and preferred forum for residential building defect claims. It is designed to be a faster, cheaper, and less formal alternative to court. Its key features include:

  • Jurisdiction: NCAT can hear and determine home building claims up to a value of $500,000
  • Cost-Effectiveness: Filing fees are significantly lower than in the courts, and the streamlined process helps contain legal costs
  • Accessibility: The rules of evidence are more flexible, and the environment is less intimidating, making it more accessible for the owners corporations

For high-value or particularly complex disputes, the courts are the necessary forum. Claims are directed to different courts based on their value:

  • District Court handles claims between $500,001 and $750,000
  • Supreme Court manages claims exceeding $750,000

Court proceedings are substantially pricier, significantly slower, and bound by strict formal procedures, making NCAT the strategically preferred option for most claims within its jurisdiction.

A Guide to NCAT Proceedings for Strata Defects

Commencing Your Building Defect Claim

After the mandatory NSW Fair Trading dispute resolution process has been attempted unsuccessfully, the owners corporation can commence formal proceedings. The primary forum for this is NCAT.

To begin the process, an application for a home building dispute must be lodged online through the NCAT Online Services portal. This application requires precise information to avoid unnecessary delays.

Key details that must be included in your application:

Application RequirementDetails
Correct Party InformationThe full and correct legal names, addresses, and ABN/ACN for all parties, including the owners corporation and the responsible builder or developer.
Orders SoughtA clear and specific statement of the orders you want the Tribunal to make, typically asking for payment for rectification costs as detailed in your expert report.
Essential AttachmentsYour application must be supported by crucial documents, including the letter from NSW Fair Trading authorising you to proceed and your expert evidence (including the Scott Schedule).

Navigating Directions Hearings & Conciliation

Once NCAT accepts your application, the formal tribunal process begins. The first appearance is typically a Directions Hearing—a brief session where a Tribunal Member manages the case by setting a clear timetable for the proceedings.

During this hearing, the Member will issue legally binding “directions” that establish deadlines for specific tasks. These often include:

  • Filing and serving points of claim and defence
  • Exchanging all evidence, such as expert reports, Scott Schedules, and witness statements
  • Directing the parties’ experts to meet in a “conclave” to identify areas of agreement and disagreement, which helps narrow the issues in dispute

The Tribunal is required to encourage settlement and will usually direct the parties to a compulsory conciliation session. This private negotiation, facilitated by a Tribunal Member or conciliator, provides a critical opportunity to resolve the building dispute before incurring the costs of a final hearing.

Understanding NCAT Orders & Enforcement

If the matter does not settle at conciliation and proceeds to a final hearing, the Tribunal Member will decide and issue legally binding orders. In building defect claims, the two most common orders are:

Order TypeDescriptionEnforcement for Non-Compliance
Work OrdersCompels the builder to return to the property and rectify the work. This is the preferred outcome under section 48MA of the Home Building Act 1989 (NSW).Failure to comply can be reported to NSW Fair Trading, potentially leading to disciplinary action against the builder, including licence suspension or cancellation.
Money OrdersRequires the builder or developer to pay the owners corporation a sum of money for rectification costs. Issued when it is inappropriate for the builder to return to the site.Can be certified and registered as a judgment in the NSW Local Court, allowing the owners corporation to pursue debt recovery actions like garnishee orders.

NCAT orders are legally enforceable. If a party fails to comply:

  • A Money Order can be certified and registered as a judgment in the NSW Local Court, allowing the owners corporation to pursue debt recovery actions like garnishee orders.
  • Failure to comply with a Work Order can be reported to NSW Fair Trading, potentially leading to disciplinary action against the builder, including suspending or cancelling their licence.

When to Escalate Your Building Dispute to Court

Jurisdictional Limits & Claim Complexity

The primary factor determining whether a building dispute is heard in NCAT or a court is the monetary value of the claim. The legal framework in NSW establishes a clear hierarchy for where a building defect claim should be filed.

This hierarchy is based on the following financial thresholds:

ForumMonetary Jurisdiction
NSW Civil and Administrative TribunalHears home building claims valued up to $500,000.
The District Court of NSWHears claims between $500,001 and $750,000.
Supreme Court of NSWManages claims exceeding $750,000.

Beyond the monetary value, the complexity of the dispute is also a critical consideration. While NCAT is the designated forum for most residential building work disputes, the courts are better equipped for certain types of cases, including:

  • Cases involving intricate legal issues
  • Professional negligence claims against architects or engineers
  • Large-scale disputes with multiple parties

The Supreme Court, in particular, can handle matters outside NCAT’s statutory powers, such as claims for certain types of equitable relief.

A crucial strategic point for an owners corporation is the “transfer power” established under the Home Building Act 1989 (NSW). This legislation designates NCAT as the primary body for resolving building claims. If a claim that falls within NCAT’s monetary limit is incorrectly commenced in a court, the builder, or developer can apply to have it transferred to NCAT, which may result in an adverse costs order against the party that filed in the wrong forum.

Comparing the Costs, Timeframes & Formality

The decision to escalate a building dispute to court carries significant implications for the proceedings’ cost, duration, and procedural nature. The differences between NCAT and the courts are stark, making NCAT the strategically preferred option for most claims within its jurisdiction.

Cost Considerations

Court proceedings are substantially pricier than NCAT for several reasons:

  • Filing fees for the District or Supreme Court are in the thousands of dollars, compared to a few hundred for NCAT
  • Courts impose daily hearing fees
  • Legal costs for representation are significantly higher
  • Even if successful, a winning party in court typically only recovers a portion of their actual legal expenses

Timeframe Differences

The timeframes for resolution also differ dramatically between the two forums:

  • NCAT is designed for faster outcomes, with matters often listed for an initial hearing within weeks or months
  • The court system is notoriously slow, with a formal, multi-stage process that can take two to four years, or even longer, to reach a final hearing

Formality Levels

Finally, the level of formality is a key distinction between the two options:

  • NCAT operates with more flexibility, applying the rules of evidence less rigidly in an environment designed to be more accessible
  • The courts are highly formal, governed by strict procedural rules, making experienced legal representation practically essential to navigate the complex and often intimidating process

Conclusion

Resolving a strata building defect in NSW requires a structured approach, from identifying and documenting the issue to engaging legal and technical experts. Navigating the dispute resolution pathways through informal negotiation, NCAT, or the courts is critical for a successful outcome.

If you are dealing with a building defect, seeking professional legal advice is crucial to protect your rights and achieve a successful resolution. Contact the specialist lawyers at PBL Law Group today for trusted expertise and guidance to confidently navigate your building dispute.

Frequently Asked Questions (FAQ)

Loading

Loading

Last Updated on July 13, 2025
Jump to...

Book a 15-Min Consultation​

Rated 5-Star By Our Clients

Latest insights & Practical Guides

Speak to us Now or Request a Consultation.

We will call you within 24 hours.

How Can Our Expert Lawyers Help?

Strata Law

Property and strata disputes, building defects claims, setting up new Owners Corporations and more…

Construction & Building Law

Construction and building disputes, building defects, delays and claims, debt recovery and more…

International Estate Planning

Cross-border estate planning, international wills and trusts, tax-efficient wealth transfer strategies and more…

Commercial & Business Law

Starting and scaling your business, banking and business financing, bankruptcy and insolvency and more…

Planning & Environment Law

Environment and planning regulation, land and environment court disputes, sub-divisions and more…

Wills & Estates

Creating, updating and contesting wills, estate planning and administration, probate applications and more…

Thank You For Your Request.

We’ve received your consultation request and will contact you within the next 24 hours (excluding weekends).

Google 5-star review: Excellent