Damages for Defective Building Work in NSW: How Much is Recoverable for Construction Defects?

9 min read
Real estate agents reviewing building plans at a construction site.
Jump to...

Introduction

Construction defects are common in NSW, often leading to significant financial loss and disputes between property owners and builders. Understanding how damages for defective building work are calculated is essential when a breach of a construction contract or statutory duty, such as those under the Home Building Act 1989 (NSW), occurs. This guide addresses how much compensation is recoverable for such defects under NSW construction law.

The primary goal when awarding damages is to place the innocent party in the position they would have been in had the defective work not occurred, typically by covering the cost of rectification. However, determining the final award involves navigating key legal principles, including assessing whether rectification is reasonable, the potential application of Diminution in Value Assessment (DIV) as an alternative measure of damages, and the impact of statutory and contractual limitations. This article provides an overview of these principles to clarify the potential recovery for defective work.

The Primary Measure: Cost of Rectification Damages

The Principle from Bellgrove v Eldridge [1954] 90 CLR 613

When defective building work arises from a breach of contract, the primary measure of damages awarded by NSW courts is the cost required to rectify the defects. This approach serves a specific purpose — to place the innocent party, typically the owner, in the financial position they would have occupied had the construction contract appropriately been performed without the breach.

The foundational principle stems from the High Court of Australia’s decision in Bellgrove v Eldridge [1954] 90 CLR 613 This landmark case established that an owner is entitled to recover the cost necessary to make the defective work conform to the contract’s plans and specifications. Moreover, this measure applies even if substantial work is required to achieve conformity, such as:

  • Demolition of existing structures
  • Complete rebuilding of certain elements

The court rejected the idea that damages should be the DIV, instead emphasising the owner’s right to the performance interest of the contract. Ultimately, the goal is to ensure the owner receives the building they bargained for.

The “Necessary and Reasonable” Qualification

While the cost of rectification is the standard measure, the High Court in Bellgrove v Eldridge [1954] 90 CLR 613 introduced a crucial qualification. The proposed rectification work must be both:

  • Necessary to achieve conformity with the contract
  • A reasonable course of action to adopt

Necessity means the work is required to make the building meet the contractual standards. On the other hand, reasonableness is assessed as a question of fact in each case. It involves considering whether the rectification is a sensible and appropriate response to the defect.

The High Court later clarified in Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8 that the test for unreasonableness is high, stating that rectification costs should be awarded unless the circumstances are “fairly exceptional.”

Unreasonableness might be argued if the cost of rectification is “wholly disproportionate” to the benefit the owner would gain from the repair, as seen in cases like Ruxley Electronics & Construction Ltd v Forsyth [1995] 3 All ER 268. However, Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8 decision reinforces that the owner’s entitlement to the contracted outcome is paramount, making the cost of rectification the ruling measure in most situations involving defective building work.

When Rectification is Unreasonable: Diminution in Value

Defining Diminution in Value

DIV is an alternative measure of damages when the primary approach, the cost of rectification, is not applicable. It represents the difference between:

  • The market value of the property as it stands with the defects
  • The hypothetical market value it would have had if the building work had been completed without those defects

This measure focuses on the financial impact of the defect on the property’s overall worth, rather than the physical cost to address the issue.

Circumstances Triggering Diminution in Value Assessment

Courts or tribunals typically award damages based on DIV only when ordering rectification is deemed unreasonable. The primary circumstance triggering a DIV assessment is when the cost of the necessary rectification work is considered “wholly disproportionate” to the actual benefit the owner would gain from the repairs.

This principle is illustrated in cases such as Ruxley Electronics & Construction Ltd v Forsyth [1995] 3 All ER 268, where the cost to rebuild a swimming pool to the exact specified depth was out of all proportion to the minor difference in utility or value.

Other situations where DIV might be considered include:

  • Where the defect is minor or aesthetic and does not significantly impact the property’s use or structural integrity
  • Where rectification might involve demolishing otherwise sound work, leading to economic waste
  • In “fairly exceptional circumstances” where the test of unreasonableness, as set out in Bellgrove v Eldridge [1954] 90 CLR 613 and affirmed in Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8, is met

Whether rectification is unreasonable is a question of fact determined in light of the case’s circumstances. The owner’s intention regarding the repairs may also be considered part of this assessment.

The Importance of Pleading and Proving ‘Diminution in Value Assessment’

If a court determines that the cost of rectification for a particular defect is unreasonable, the burden shifts to the claimant to establish the loss based on DIV. The claimant must have:

  • Pleaded DIV as an alternative measure
  • Provided sufficient evidence to quantify this loss

This evidence typically involves comparing the property’s value with the defect against its value without the defect, often requiring expert valuation reports.

Failure to provide evidence demonstrating a DIV can have significant consequences. As seen in Westpoint Management Ltd v Chocolate Factory Apartments Ltd [2007] NSWCA 253, rectification was unreasonable for certain defects. However, the claimant provided no evidence of DIV; only nominal damages (a token sum) may be awarded for that breach. This highlights the strategic importance of anticipating the possibility that rectification might be deemed unreasonable and preparing to prove loss based on DIV as a fallback position.

Recovering Consequential Economic Losses

Examples of Recoverable Incidental Costs

Beyond the primary measure of damages, such as the cost of rectification, property owners may also recover additional financial losses incurred as a direct result of defective building work. These are often termed consequential or incidental economic losses.

To be recoverable, these costs must be proven to be a necessary consequence of the builder’s breach of contract or statutory duty. Common examples of such recoverable costs include:

  • Lost Rent: If the defective work prevents an investment property from being leased or reduces its rental income during the period affected by the defect or its rectification.
  • Relocation Expenses: Costs associated with moving occupants or belongings out of the property while defects are assessed or repaired.
  • Alternative Accommodation: Reasonable expenses for temporary housing if the property becomes uninhabitable due to the defects or the rectification process.
  • Expert Investigation Fees: Costs paid to building consultants, engineers, quantity of surveyors, or other experts needed to investigate the defects, determine the cause, scope the necessary rectification, and provide reports for the claim.
  • Supervision Costs: Fees for consultants required to oversee and manage the rectification works performed by another contractor.
  • Damage to Other Property: Costs to repair damage caused to other parts of the building or its contents that directly resulted from the initial defect, such as water damage from a leaking roof.
  • Increased Insurance Premiums: If the defects directly lead to higher insurance costs for the property owner.
  • Refinancing Costs: Expenses incurred in refinancing that were potentially necessitated by the defect issues.

Causation and Foreseeability Requirements

Recovering consequential economic losses is not automatic; specific legal requirements must be met. The claimant is responsible for proving that these additional losses satisfy the tests of causation and foreseeability.

A causal link between the builder’s breach (the defective work) and the consequential loss suffered must be established. The loss must be shown to flow directly from the defect or the necessary rectification process.

Secondly, the loss must not be too remote. This generally means the loss must have been reasonably foreseeable by the parties when the contract was made, or the statutory duty arose as a probable result of such a breach.

Courts distinguish between direct losses, which arise naturally in the ordinary course of things, and indirect or consequential losses, which may only be recoverable if they arise from special circumstances known to the defaulting party.

The Design and Building Practitioners Act 2020 (NSW) explicitly allows claims for “economic loss,” potentially supporting claims for a range of consequential financial losses stemming from breaches of its statutory duty of care.

Factors Influencing the Final Quantum Awarded

Assessing the Reasonableness of Rectification Costs (Including Betterment)

Even when the cost of rectification is the accepted measure of damages for defective building work, the specific amount claimed must be proven reasonable. Courts and tribunals evaluate reasonableness by considering several factors related to the proposed rectification work. This assessment examines both the necessity of the work and the associated costs.

Key considerations include:

  • Necessity: Is the proposed work required to bring the building to conformity with the construction contract or relevant statutory standards?
  • Proportionality: Is the cost of the rectification wholly disproportionate to the benefit the owner will gain? For instance, courts may find it unreasonable to award substantial costs for defects that do not pose a significant risk or impact the building’s utility.
  • Alternatives: Are there less expensive, yet adequate, methods available to rectify the defect and achieve conformity?
  • Owner’s Intention: While not always decisive, the court might consider if the owner genuinely intends to undertake the rectification for which damages are claimed.

A common issue in assessing reasonableness is “betterment.” This occurs when rectification results in the owner receiving a property superior to what was originally contracted for, perhaps due to newer materials or improved specifications. The principle is that damages should compensate for the loss, not provide a windfall.

However, a deduction for betterment from the damages award is not automatic. Courts typically only reduce the award if:

  • The owner chose a superior repair method when a cheaper, conforming alternative was reasonably available.
  • The improvement was unavoidable (e.g., due to updated standards or material availability), but it provided a clear, quantifiable financial benefit to the owner that was not speculative.

Courts often hesitate to deduct for betterment if the improvement was necessary for rectifying the builder’s defective work. The onus is generally on the defendant (the builder or developer) to prove that betterment has occurred and to quantify the appropriate deduction.

The Claimant’s Duty to Mitigate Loss

A fundamental legal principle requires the party who has suffered the loss (the claimant) due to a breach of contract or duty to take reasonable steps to mitigate or minimise that loss. Claimants cannot recover damages for losses that they could have reasonably avoided. This duty applies to claims for damages arising from defective building work.

In NSW, for residential building work contracts under the Home Building Act 1989 (NSW), section 18BA outlines specific mitigation duties for homeowners or subsequent owners entitled to statutory warranties. These duties include:

  • Making reasonable efforts to notify the builder and developer in writing of the breach (defect) within 6 months after it becomes apparent.
  • Allowing the builder reasonable access to the property to inspect and rectify the defective work.
  • Not unreasonably refusing the builder access for rectification purposes.

A crucial aspect of mitigation is whether the owner must allow the original builder the opportunity to rectify the defects. Generally, providing this opportunity is considered a reasonable step, as the original builder may be able to address the issue at a lower cost. Furthermore, the NSW Civil and Administrative Tribunal (NCAT) views rectification by the responsible builder as the preferred outcome under section 48MA of the Home Building Act 1989 (NSW).

However, an owner can refuse access if it is reasonable. Reasonableness is assessed based on the specific circumstances, including:

  • Loss of Confidence: If the owner has reasonably lost confidence in the builder’s ability or willingness to rectify the work properly, often due to the poor quality of the original work, previous failed repair attempts, or unprofessional conduct.
  • Builder’s Response: The builder’s reaction to the defect notification, such as denying responsibility, proposing inadequate repairs, or failing to engage constructively.
  • Severity of Defects: The nature and extent of the defects may make it unreasonable to trust the original builder with repairs.

The builder carries the burden of proving that the owner acted unreasonably in failing to mitigate their loss. A failure to mitigate does not defeat the claim entirely, but may lead to a reduction in the damages awarded.

The Crucial Role of Expert Evidence

Expert evidence is almost always essential in construction defect disputes to establish the existence of defects and the quantum of recoverable damages. Courts and tribunals rely heavily on independent expert opinions to understand technical difficulties, determine compliance with standards, assess appropriate rectification methods, and verify the reasonableness of repair costs.

Common types of experts involved include:

  • Building Consultants: Conduct assessments, compare work against plans and standards, and scope rectification needs.
  • Engineers (e.g., Structural, Fire Safety, Hydraulic, Façade): Offer specialist technical opinions on specific types of defects and their causes.
  • Quantity of Surveyors: Specialise in construction cost estimation, providing detailed breakdowns of rectification costs necessary to prove the financial quantum of the claim.

Expert reports must be thorough, objective, and reasoned, outlining the expert’s qualifications, the basis of their opinions, and any supporting standards or tests. In NCAT proceedings involving larger claims under the Home Building Act 1989 (NSW), experts must comply with specific requirements, including the Expert Witness Code of Conduct outlined in NCAT Procedural Direction 3.

A common tool for presenting complex defect claims is the Scott Schedule. This is typically a table that itemises each alleged defect, outlining:

  • The claimant’s description of the defect.
  • The claimant’s proposed rectification method and claimed cost (supported by expert evidence).
  • The respondent’s response, including any alternative methods or costs.
  • References to the relevant expert reports for each item.

Scott Schedules help clarify disputed issues, compare expert opinions, facilitate negotiations, and streamline the hearing process. The quality and credibility of expert evidence, often presented via Scott Schedules, are frequently decisive in determining the final damages award.

Statutory Limitation Periods 

Claimants must commence legal proceedings within strict statutory time limits, or their claim may be barred. Different limitation periods apply depending on the legal pathway chosen.

Under the Home Building Act 1989 (NSW), the time limits for bringing claims for breach of statutory warranty are:

  • Major Defects: Within 6 years from the completion of the work.
  • Other Defects: Within 2 years from the completion of the work.
  • Completion Date: For strata schemes, completion is usually when the occupation certificate for the whole building is issued.
  • Late Discovery Extension: If a defect becomes apparent in the past 6 months of the relevant 2 or 6-year period, the claimant has an additional 6 months from the end of that original period to commence proceedings.

For claims under the Design and Building Practitioners Act 2020 (NSW) statutory duty of care or common law negligence for economic loss arising from building work:

  • Standard Period: Generally, proceedings must commence within 6 years from the date the cause of action accrues, when the economic loss caused by the defect becomes reasonably apparent.
  • Long-Stop Period: Section 6.20 of the Environmental Planning and Assessment Act 1979 (NSW) imposes an absolute 10-year long-stop period. No action can be commenced more than 10 years after the completion of the works, regardless of when the loss became apparent.
  • Effective Deadline: The deadline is 6 years from reasonable loss discovery or 10 years from completion.

Home Building Compensation Fund Caps

The Home Building Compensation Fund (HBCF) is a last-resort insurance scheme in NSW for residential building work valued over $20,000. It compensates homeowners for losses from incomplete or defective work only when the builder cannot, due to specific trigger events:

  • Insolvency
  • Death
  • Disappearance
  • Licence suspension for non-compliance with a money order.

HBCF coverage periods mirror the Home Building Act 1989 (NSW) warranty periods: 6 years post-completion for major defects and 2 years for non-major defects. However, payouts are subject to significant financial caps:

  • Maximum Payout: $340,000 per dwelling for policies issued from 1 February 2012 onwards. This covers the total of all claims (defects and non-completion).
  • Non-Completion Sub-Limit: Compensation for failure to complete the work is capped at 20% of the contract price.

These caps, particularly the $340,000 limit unchanged since 2012, may be insufficient to cover the full cost of rectification or completion in today’s market due to rising construction costs.

Impact of Contractual Provisions

Construction contracts often contain clauses that manage defect rectification, such as Defects Liability Periods (DLPs) and final certificate mechanisms.

  • Defects Liability Period (DLP): This is a period after practical completion (e.g., 13 weeks, 6 months, 12 months) during which the contractor is contractually obliged to rectify notified defects. The DLP is distinct from and usually shorter than the statutory warranty periods under the Home Building Act 1989 (NSW).
  • Final Certificates: Some contracts (like AS forms) use final certificates issued after the DLP. Depending on the wording, these might be considered conclusive evidence of satisfaction regarding patent (obvious) defects apparent during the DLP.

While these contractual provisions provide a framework for defect management, they generally cannot override or exclude statutory rights, such as the warranties under the Home Building Act 1989 (NSW) or the duty of care under the Design and Building Practitioners Act 2020 (NSW). However, case law like Parkview Constructions Pty Ltd v Futuroscop Enterprises Pty Ltd [2023] NSWSC 178 suggests that if not carefully drafted or managed, DLP and final certificate clauses could potentially be interpreted as a complete code that bars common law damages claims for patent defects not addressed through the contractual process.

Conclusion

Determining the recoverable damages for defective building work in NSW primarily hinges on the reasonable cost of rectification, ensuring the owner receives the building quality they contracted for, as established in cases like Bellgrove v Eldridge [1954] 90 CLR 613. However, this is qualified by reasonableness, with DIV considered only when rectification is disproportionate, alongside the potential recovery of consequential losses and the critical need for timely action within statutory limitation periods and robust expert evidence.

Navigating the complexities of construction defect claims requires specialised legal knowledge to protect your interests effectively. For trusted expertise and clear guidance on quantifying damages or resolving disputes related to defective work in NSW, contact PBL Law Group’s specialist construction lawyers today.

Frequently Asked Questions

Loading

Loading

Last Updated on March 1, 2025
Picture of Authored By<br>Raea Khan
Authored By
Raea Khan

Director Lawyer, PBL Law Group

Jump to...

Book a 15-Min Consultation​

Rated 5-Star By Our Clients

Latest insights & Practical Guides

Speak to us Now or Request a Consultation.

We will call you within 24 hours.

How Can Our Expert Lawyers Help?

Strata Law

Property and strata disputes, building defects claims, setting up new Owners Corporations and more…

Construction & Building Law

Construction and building disputes, building defects, delays and claims, debt recovery and more…

International Estate Planning

Cross-border estate planning, international wills and trusts, tax-efficient wealth transfer strategies and more…

Commercial & Business Law

Starting and scaling your business, banking and business financing, bankruptcy and insolvency and more…

Planning & Environment Law

Environment and planning regulation, land and environment court disputes, sub-divisions and more…

Wills & Estates

Creating, updating and contesting wills, estate planning and administration, probate applications and more…

Thank You For Your Request.

We’ve received your consultation request and will contact you within the next 24 hours (excluding weekends).

Google 5-star review: Excellent